What do you think? Take the Survey!

Public Meetings

public involvement Throughout the planning effort we will be working with key city staff and the project will be overseen by a steering committee made up of experts from all disciplines. All steering committee meetings will be open to the public.

Steering Committee Members

The Steering Committee will meet at the Zeidler Building, 841 N Broadway, 7th Floor Conference Room, on the following dates:

All meetings take place from 8:30 - 10:00 AM

The project start date was April 30th, 2008 and will be finished by December 2009.

Milwaukee Bike Plan General Timeline

Comprehensive Public Outreach Plan Ongoing
Existing Condition Inventory and Evaluation Complete
Needs Analysis Fall/Winter
Present Plan Ideas and Research Findings Complete
Start Developing Recommendations December 2008
Evaluate and Update Design Guidelines Spring 2009
Present Recommendations May 2009
Draft Plan October 2009
Present Draft Plan November 2009
Final Plan December 2009

(Public Meetings in Bold)

The first public meeting was an open house on November 13th from
4:30 - 8:00 pm at the Washington Park Senior Center on 4420 W. Vliet
Street. The meeting was well attended with 71 registered attendees.